Original source

Summary

pv magazine USA, reporting on a Reuters Events analysis, documents that lead times for high-capacity power transformers have stretched to as long as four years per PwC analysts — the freshest (May 2026) lead-time figure available, distinct from the 128–160-week figures the wiki holds from the January 2026 Transformers in 2026 — POWER Magazine - 2026-01-02 piece. Transformer availability is now “dictating power project schedules across the country.” The article names grain-oriented electrical steel and copper scarcity as a core driver of the crunch, and reports developers buying factory production slots before they have even sited a project.

Key Points

  • Four-year lead time for high-capacity units, per PwC analysts (the headline figure; cause = “surging demand and raw material shortages”).
  • Wood Mackenzie demand growth, 2019–2025: generator step-up (GSU) transformers +274%; substation transformers +116%. (Note: this is a 2019–2025 substation figure; the Transformers in 2026 — POWER Magazine - 2026-01-02 page carries a separate “+119% power-transformer demand since 2019” figure — different transformer classes, do not conflate.)
  • Prices +~80% over the last five years.
  • Grain-oriented electrical steel + copper named as the binding raw-material constraint; “because domestic production of material is constrained, manufacturers and developers remain heavily dependent on imports.” (See Cleveland-Cliffs — the sole U.S. GOES producer.)
  • Procurement behavior shift: firms purchasing production slots at a premium before finalizing a project site; others refurbishing older units to bridge the gap (Michael Novev, Burns & McDonnell).
  • Domestic capacity response: Hitachi Energy >$1B incl. a South Boston plant online 2028; Siemens raised its Charlotte, NC commitment to $421M.
  • Workaround: large data center developers turning to on-site power generation to bypass interconnection queues; utility-scale renewables risk becoming stranded assets if they cannot secure transformers in time.

Newsletter Angles

  • The four-year number is the cleaner anchor than 128–160 weeks. For the June 5 flagship’s grid layer, “four years” (PwC, May 2026) is the freshest lead-time figure and lands harder than the spent week-count. This source is what lets the piece cite it.
  • Grid-layer raw-material chokepoint pairs with Cleveland-Cliffs. This piece independently confirms GOES as a binding constraint — the chokepoint-within-the-chokepoint that the Cleveland-Cliffs Weirton Transformer Plant — Utility Dive - 2024-08-06 source makes specific (one domestic mill at Butler, PA).
  • The fix has its own lead time. Hitachi’s South Boston plant opens 2028; the supply gap persists “for years.” Extends AI Buildout Grid Constraint and the “check the lead time on the fix” framing.

Entities Mentioned

  • Cleveland-Cliffs — not named in the article, but the “constrained domestic GOES production” it describes traces to Cliffs as the sole U.S. producer
  • Wood Mackenzie — demand-growth data source
  • Hitachi Energy — >$1B investment incl. South Boston plant (2028)
  • Siemens Energy — $421M Charlotte, NC transformer factory
  • Burns & McDonnell (Michael Novev) — procurement-strategy commentary

Concepts Mentioned

Quotes

“A combination of surging demand and raw material shortages has pushed lead times for high capacity units to as long as four years, according to analysts from PwC.”

Notes

Trade-press synthesis of a Reuters Events report; figures attributed to PwC (lead times) and Wood Mackenzie (demand). The substation +116% figure here is 2019–2025; the POWER Magazine page’s +119% is the power-transformer class — keep distinct. Retrieved via Claude Chrome extension (WebFetch 403); raw file saved.